Construction Update – July 2017

After breaking ground at Industria Nunawading in May, Stage 1 construction continues to progress well and is on track for completion in May 2018. We are now nearing the completion of the earth works with all footings for the warehouses to be finished this week. In ground plumbing and electrical are well underway and will be completed in a couple of weeks. Structural works are commencing this Wednesday with the forming of ground slabs for warehouses 35-41 and the remainder of Stage 1 units to be started in the coming weeks.